The challenge
2R Control Automation Sdn. Bhd. was appointed by Green Residence Management to investigate inconsistent electricity bills and verify the accuracy of electricity consumption charges.
What 2R did
Through detailed electrical inspections, power measurements, and meter accuracy assessments, our engineering team identified electricity meter discrepancies across multiple residential units, contributing to billing irregularities. The investigation provided technical findings to support the management's review of electricity charges with Tenaga Nasional Berhad (TNB).
Outcome
As a result, Green Residence successfully received an electricity bill credit adjustment of RM54,713.20 from TNB, demonstrating 2R's expertise in electricity billing investigations and helping building management recover overcharged electricity costs.
Systems in this type of building
- LED panels · efficient fittings, at the light level the task needs
- Occupancy sensor · switches lights off in empty areas
- Daylight · lights near the windows can dim when there's enough daylight
- Lighting board · where lighting circuits are measured and scheduled
- Lux meter · measures light levels at the desk: Kyoritsu 5202
Illustration of typical systems, not a client's plant.
Equipment 2R uses here
- Meatrol Mi550 · Pumps
- Kyoritsu 5202 · Lighting levels
Typical instruments for this type of site, from 2R's own equipment.
More in Residential & Strata
- Electricity Usage Investigation & Energy Audit for Palm Garden (2023)Other · 2023RM53,177.90 TNB Refund
- Electricity Usage Investigation & Energy Audit for Vina Residency (2022)Other · 2022RM749,249.77 TNB Refund
- Energy Audit for Gravit8 @ Klang South (2022)Energy audit · 202225% Potential energy saving
- Electricity Usage Investigation & Energy Audit for Concerto North KiaraOther22 KUPM Meters Confirmed and Rectified by TNB
- Electricity Usage Investigation & Energy Audit for Damai HillparkOtherRM104,022.45 TNB Refund
- Electricity Usage Investigation & Energy Audit for Impiria Residensi KlangOtherRM269,679.50 TNB Refund
Get this for your facility
Tell us about your building or plant and we'll recommend the right next step: an audit, an energy-saving project or EECA compliance support.